Boston vs. Quincy Demolition Permits

Boston, in Suffolk County, and Quincy, in Norfolk County, run different demolition-permit regimes. Boston puts a Landmarks Commission review — Article 85 (Boston Landmarks Commission) — ahead of the demolition permit; Quincy’s Inspectional Services checklist is built around utility sign-offs and site conditions. This page puts the two side by side, with every rule linked to the city that publishes it. Other cities and towns in Suffolk and Norfolk County have their own requirements; the authority for each is that municipality’s building department.

Side by side

Boston (Suffolk County)Quincy (Norfolk County)
AuthorityBoston Landmarks Commission for Article 85; Inspectional Services for the demolition permit. — Boston Landmarks Commission, Boston Inspectional ServicesInspectional Services, Building Department. — City of Quincy Inspectional Services
What triggers itBefore demolishing a building in Boston you must submit an Article 85 application. Scope: all buildings in Downtown or Harborpark, all other buildings at least 50 years of age, and all buildings in a Neighborhood Design Overlay District. — Boston Landmarks CommissionThis checklist governs a building permit to perform demolition activities. — City of Quincy Inspectional Services
Where to applySince May 23, 2022, only through the Boston Landmarks Commission online portal — no paper, no email. The signature page must be notarized. — Boston Landmarks CommissionOnline, through the City’s OpenGov permit portal. — City of Quincy Inspectional Services
Review clock10 calendar days of staff review from a complete application; a public hearing within 30 days if the building is found significant. — Boston Landmarks Commission If the Commission finds a significant building subject to demolition delay, the Commissioner of Inspectional Services is notified not to issue a demolition permit until ninety (90) days have elapsed following the close of the public hearing. — Boston Landmarks CommissionThe checklist does not state a review period. Ask Inspectional Services, Building Department. — City of Quincy Inspectional Services
UtilitiesShut-off notices from underground and overhead utilities: gas, electrical, telephone, cable. — Boston Inspectional ServicesA natural gas utility letter stating when service was terminated at the street; an electric utility letter stating the same. — City of Quincy Inspectional Services
Water and sewerA closed Boston Water and Sewer Commission general service agreement. — Boston Inspectional ServicesQuincy Water Billing Office approval that the water meter was removed by City personnel; Quincy Sewer/Drain Department approval that service was terminated at the street. — City of Quincy Inspectional Services
Dig Safe and street workA Dig Safe reference number. — Boston Inspectional ServicesA Dig Safe letter or number; a street opening / trench permit from the Engineering Department. Street work may only be performed by approved contractors. — City of Quincy Inspectional Services
Hazardous materialsMassDEP approval for hazardous materials. — Boston Inspectional ServicesUnder Health Department approval, the checklist asks for a hazardous material assessment report if applicable, and a copy of the DEP notification for commercial, industrial and residential buildings over twenty units. — City of Quincy Inspectional Services
Site conditionsNot among the Inspectional Services items listed on this page. Ask Inspectional Services. — Boston Inspectional ServicesA hydrant meter for dust control, or an invoice for a water truck. Bait boxes every 40’ of site perimeter, inspected bi-weekly. — City of Quincy Inspectional Services

Boston: the Article 85 path

  • Before demolishing a building in Boston you must submit an Article 85 application. — Boston Landmarks Commission
  • Scope: all buildings in Downtown or Harborpark, all other buildings at least 50 years of age, and all buildings in a Neighborhood Design Overlay District. — Boston Landmarks Commission
  • Article 85 was added to the Boston Zoning Code in 1995. — Boston Landmarks Commission
  • Since May 23, 2022 applications are accepted only through the Boston Landmarks Commission online portal — no paper, no email. The signature page must be notarized. — Boston Landmarks Commission
  • The 10-day staff review does not begin until the application is complete. — Boston Landmarks Commission
  • The Landmarks Commission page says staff respond with a significance determination within 10 calendar days of marking the application complete. — Boston Landmarks Commission
  • Within 10 calendar days of a complete application, staff determine whether the building is significant; if it is, the Landmarks Commission schedules a public hearing within 30 days. — Boston Landmarks Commission
  • If the Commission finds a significant building subject to demolition delay, the Commissioner of Inspectional Services is notified not to issue a demolition permit until ninety (90) days have elapsed following the close of the public hearing. — Boston Landmarks Commission

Boston: the Inspectional Services document set

Also required for the demolition permit: shut-off notices from underground and overhead utilities (gas, electrical, telephone, cable); a closed Boston Water and Sewer Commission general service agreement; MassDEP approval for hazardous materials; and a Dig Safe reference number. — Boston Inspectional Services

Quincy: the demolition checklist

This checklist governs a building permit to perform demolition activities. — City of Quincy Inspectional Services

Questions to ask, and whom to ask

  • Boston: is the building in Downtown or Harborpark, at least 50 years of age, or in a Neighborhood Design Overlay District — and so within Article 85? — ask the Boston Landmarks Commission (Boston Landmarks Commission)
  • Boston: is the Article 85 application complete, so that the ten-day staff review has started? — ask the Boston Landmarks Commission (Boston Landmarks Commission)
  • Boston: are the utility shut-off notices, the closed Boston Water and Sewer Commission agreement, the MassDEP hazardous-materials approval, and the Dig Safe reference number in hand? — ask Inspectional Services (Boston Inspectional Services)
  • Quincy: does this scope require a building permit to perform demolition activities, and which checklist items apply? — ask Inspectional Services, Building Department (City of Quincy Inspectional Services)
  • Quincy: have the gas and electric utility letters, the Water Billing Office and Sewer/Drain approvals, and the Dig Safe letter or number been obtained? — ask Inspectional Services, Building Department (City of Quincy Inspectional Services)

Each city on its own: Boston Demolition Permit Guide: Dorchester & South Boston · Quincy Demolition Permit Guide

Any scope of work that requires a state license is performed by licensed specialists that D. Clancy & Sons coordinates as part of the project.

Sources

  1. Boston Landmarks Commission — Article 85 Demolition Delay (dated December 12, 2025; checked November 8, 2026)
  2. Boston Landmarks Commission — Article 85 Requirements: Public Hearing for Significant Structures (marked temporary, as of March 2022) (checked November 8, 2026)
  3. Boston Inspectional Services — How to get a demolition permit (dated June 1, 2026; checked November 8, 2026)
  4. City of Quincy Inspectional Services — Building Permit Checklist for Demolition Activities (Demolition Checklist R2) (checked November 8, 2026)
  5. City of Quincy Inspectional Services — Building Department (checked November 8, 2026)
  6. City of Quincy Inspectional Services — Applications and Information (checked November 8, 2026)